Receipt of Purchase order – Manufacture & Supply of Anhydrous Ammonia Storage Tank – Deepak Nitrite Limited – Rs. 11.50 Crores

 

Receipt of Award – Engineering, Civil Works, Supply, Fabrication of 3rd Coke Silos – Hindalco Industries Limited – Rs. 33.33 Crores

 

Receipt of Award – Engineering and Construction of ATF Fuel Farm and Hydrant System at Guwahati International Airport – Rs. 126.15 Crores

 

Commencement of commercial production at newly set-up unit @ Parli

 

Establishment of Unit for enhancing fabrication / manufacturing capacity

 

Receipt of Award – Fabrication of Structures for AMNS Project on Conversion Basis – Tata Projects Limited (TPL) – Rs. 25.19 Crores

 

Receipt of Award – Supply of Pressure Vessels and It’s Mandatory, Erection & Commissioning Spares- Tata Projects Limited (TPL) – Rs. 14.49 Crores

 

Receipt of Award – Engineering Equipment Installation and Commissioning works at GRSE – Tata Projects Limited (TPL) – Rs. 1716.94 Lakhs

 

Receipt of Award – Fabrication of Structures – Bharat Heavy Electricals Limited – Patratu Project – Rs. 520.80 Lakhs

 

Receipt of Award – Manufacture and Supply of Buss Loop Reactor, Buss Loop Heat Exchanger & Buss Loop Piping – Aarti Industries Limited – Dahej – Rs. 6.63 Crores

 

Modification of Award – Fabrication of Structures for TSL Project – Rs. 23.34 Crores

 

Receipt of Award – Manufacture & Supply of 10 Nos Gas to Gas Heat Exchangers – Kutch Copper Limited (100% subsidiary Adani Enterprises Limited) – Rs. 42.76 Crores

 

Receipt of Award – Fabrication and Supply of Structures for TSL IOPP – Tata Projects Limited (TPL) (Noamundi Project) – Rs. 61.77 Crores

 

Receipt of Awards – Manufacturing of two Heat Exchangers – Hindalco Industries Limited (Dahej Plant) – Rs. 6.76 Crores

 

Receipt of Awards – Construction of Absorbers for FGD at Talcher and Vallur- Rs. 20.32 Crore

 

Receipt of Award – Construction of tanks at ONGC Kakinada Site – Rs. 8.60 Crores

 

Receipt of Award – Mechanical Installation and Commissioning Works at GRSE Yard- 17.08 Crores

 

Receipt of Award – Supply of Fabricated Structures for NTPC Project – 11 Crores

 

Receipt of Award – NFC Project, Kota – 6.54 Crores

 

Receipt of Additional Order – Manufacture and Supply of Cladded Plates – 34.34 Crores

 

Receipt of Award – Convergence Chemicals Private Limited, Dahej – 9.01 Crores

 

Award of Order – NFC Kota, Shop Tanks – 17.97 Crores

 

Award of Order – Vallur – 5.14 Cr

 

Award of Order – Talcher – 15.43

 

Award of Order – BPCL Bargarh – 16.63 Crore

 

Announcement – Award of Order – 20.06.2020

 

Announcement – Award of Order – TPL Muratec – 04.12.2019

 

Announcement – Award of Order – Vedanta Limited – 04.11.2019

 

Intimation to shareholders – Updation of Details

 

Announcement – Award of Order – BHEL Patratu

In compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, we are pleased to inform that, the Company has received a Letter of Acceptance (LOA) of approx. Rs. 25.79 crores for Detail drawing preparation based on Input Design drawings provided by BHEL/PEM for Main Power House, Fabrication and supply of finished products for this package as per BOM/Drawings for 3X800 MW PVUNL BHEL, Patratu.

Announcement – Update on Credit Rating

In compliance with Regulation 30(6) & Regulation 46(2) of the SEBI (Listing Obligation and Disclosure Requirements) Regulations, 2015, we wish to inform that India Rating and Research (‘Ind-Ra’), A Fitch Group Company, has assigned the credit rating to the bank facilities of the Company.

Announcement – Award of Order – IOCL Dhumad

In compliance with Regulation 30 of the SEBI (Listing Obligation and Disclosure Requirements) Regulations, 2015, we are pleased to inform that, the Company has received a Fax of Acceptance of Rs. 95.89 Crores (Rupees Ninety-Five Crores Eighty-Nine Lacs Only) from Indian Oil Corporation Limited for detailed engineering, Supply, Fabrication, Installation, Testing and Commissioning of Storage Tanks at Dhumad, Gujarat.

Announcement – Receipt of Award – Thyssenkrupp – Reg 30

We are pleased to inform that, the Company has received a Purchase Order (PO) from Thyssenkrupp Industries India Private Limited of approx. Rs.15.00 Crores (Rupees Fifteen Crores only) (Excluding GST) for Supply of Material, Fabrication.

Announcement – Award of Order – BPCL Haveli

We are pleased to inform that, the Company has received a Letter of Acceptance(LOA) of approx. Rs. 25.73 Crores (Rupees Twenty Five Crores Seventy Three Lakhs Only), for Construction of above ground cone roof, floating roof and underground tank for hydrocarbon product storage at Haveli, Pune.

Announcement – Award of Order

We are pleased to inform that, the Company has received a Letter of Intent of approx. Rs. 28.94 Crores (Rupees Twenty Eight Crores Ninety Four Lakhs Only), for Design, engineering, the supply of equipment’s, piping, instruments, electricals, erection, commissioning spares etc., for Dross Refining Project from Tata Projects Limited.

Announcement – Award of Order

We are pleased to inform that, the Company has received a letter of intent for approx. Rs. 24.15 Crores from GMR Hyderabad International Airport Limited for design, supply and construction of ATF tanks and associated works on EPC Basis in the existing fuel farm within Rajiv Gandhi International Airport, Shamshabad, Hyderabad.

Announcement – Award of Order

We are pleased to inform that, the Company has received a Letter of Intent of approx. Rs.13.53 Crores (Rupees Thirteen Crores Fifty Three Lakhs Only), for Design, engineering, supply of equipment’s, piping, instruments, electricals, chemicals, catalyst, insulation, commissioning spares etc., Commissioning, supply of two years spare parts for Purge Gas recovery unit (PGRU) for Ammonia, Urea plant.

Announcement – Upgrade and assignment of new rating to Bank facilities

In compliance with Regulation 30(6) and 46(2) of the SEBI (Listing Obligation and Disclosure Requirements) Regulations, 2015, we wish to inform that India Rating and Research (‘Ind-Ra’), (A Fitch Group Company) has upgraded and assigned new ratings to the bank facilities of the Company. The rating letter as received from ‘Ind-Ra’ is enclosed herewith. Further, the aforesaid information is also disclosed on the website of ‘Ind-Ra’ i.e., www.indiaratings.co.in

Announcement – Change in the Registered Office Address

Dear Stakeholders, please be informed that, with effect from 23rd January 2018, the Registered Office address of the Company has changed from 11th floor, Hiranandani Knowledge Park, Technology Street, Powai, Mumbai – 400076, Maharashtra to 2nd Floor, Transocean House, Lake Boulevard Road, Hiranandani Business Park, Powai, Mumbai, Maharashtra – 400076.”

Announcement – Board Meeting – 24.10.2017, Hyderabad

“We are pleased to inform that, the Board of Directors at their Meeting held on 24th October 2017, approved the appointment of Mr. Saket Mathur as the Chief Operating Officer (COO) and Manager, Designate, of the Company w.e.f 1st November 2017. Further, Mr. Saket Mathur will take charge as COO and Manager w.e.f 1st January 2018 from Mr. Nikhil Naniwadekar, who will be moving to the holding Company i.e. Tata Projects Limited.”

Mumbai, 01st August 2017

“In compliance with Regulation 30 of the SEBI (Listing Obligation and Disclosure Requirements) Regulations, 2015, we are pleased to inform that, the Company has received orders worth Rs. 2330 Lakhs for Design, Engineering, Supply and Installation, Testing and Commissioning of Connector Fuel Pipelines including associated civil, electrical, instrumentation works.”

Mumbai, 28th June 2017

In compliance with Regulation 30(6) and 46(2) of the SEBI (Listing Obligation and Disclosure Requirements) Regulations, 2015, we wish to inform that India Rating and Research (‘Ind-Ra’), (A Fitch Group Company) has revised and assigned new ratings to the bank facilities of the Company. The report as received from ‘Ind-Ra’ is enclosed herewith. Further, the aforesaid information is also disclosed on the website of ‘Ind-Ra’ i.e., www.indiaratings.co.in

Mumbai, 19th June 2017

The Company has received an Award for Fabrication, Erection and Commissioning of Large Diameter Piping and Associated Works at Krishnapatanam. The estimated order value is Rs. 5.19 Crores.

Mumbai, 3rd April 2017

The Company has received an Award Connector Pipeline Laying and associated Works for Integrated Aviation Fuel Hydrant System at CSIA, Mumbai. The estimated order value is Rs. 12.52 Crores.

Mumbai, 26 December 2016

“The Company has received an Award for Supply of Fabricated Structure -NTPC LARA Project. The estimated order value is Rs. 4.23 Crores.”

Mumbai, 13th December 2016

The Company has received an Award for Design, Fabrication, Erection, Testing of 4 Nos. Double Deck Floating roof Type Storage Tanks at Paradeep. The estimated order value is Rs. 108 Crores.

Mumbai, 29th August 2016

“The Company has received a Letter of Award for Design, Fabrication, Erection & Testing of 05 Nos. Fixed Cone Roof Storage Tanks. The estimated order value is Rs. 24.43 Crores.”

Mumbai, 26th August 2016

The Company has received an Award for Fabrication, Installation, Testing & Commissioning of Firefighting Piping Works for Package B at Hazel. The estimated order value is Rs. 6.63 Crores.

Mumbai, 11th July 2016

“The Company has received an Award for Erection and Fabrication work for piping of Chemical Terminal at HFZ, Sharjah. The estimated order value is Rs. 10.39 Crores.”

Mumbai, 4th July 2016

“The Company has received an Award for Fabrication and supply, Fabricated steel structure, from Rolled and Built Up sections and plates including all required manufacturing operations, Inspection and Testing for RINL Vizag. The estimated order value is Rs. 11.50 Crores.”

Mumbai, 14th December 2015

“The Company has received a Purchase Order for Fabrication and Supply of Steel Building Structure for a Power plant. The estimated Order Value is Rs. 14.87 Crore.”

Mumbai, 4th December 2015

“The Company has received a Purchase Order for Fabrication and Supply of Steel Structures for a steel plant. The estimated Order Value is Rs. 10.77 Crore.”

Mumbai, 5th November 2015

“The Company has received a Purchase Order for Fabrication and Supply of Building Structure for a mining plant. The estimated Order Value is Rs. 13.26 Crore.”

Mumbai, 28th October 2015

“The Company has received Work Order for Erection and Refurbishing work for Dust Extraction System to be executed at a steel plant. The estimated Order Value is Rs. 2.56 Crore.”